Built in 1976, FL
CIPP lining 24” RCP storm drains.
Built in 1988, FL
Inspected, cleaned and restored over 3,000 LF of sovent sanitary stacks with minimal access and little or no interruption to guests.
Built in 1991, VA
Inspected, cleaned and restored over 5,300 LF of cast iron sovent sanitary riser stacks.
Built in 2008, NJ
Inspected, cleaned and restored over 2,000 LF of sanitary sovent riser stacks.
Built in 1980, FL
CIPP lining of 15,200 LF of sanitary riser stacks and underground mains approx. 1,000 LF, including bypass of an entire tower to service the underground.
4 Interconnected Buildings, Built in 1973, FL
CIPP lining underground mains and laterals approx. 20,000 LF of piping, containment, surgery center, all while fully operational.
Built in 1993, FL
CIPP lining over 1,000 LF of kitchen sanitary underground 4” and 6” cast iron piping overnight.
Built in 1954, FL
CIPP lining underground mains and laterals approx. 5,800 LF of piping.
Built in 2005, Washington, DC
Inspected, cleaned and restored cast iron sanitary sovent riser stacks and upper floor unit laterals, (after several unsuccessful attempts by previous contractors).
Built in 2006, MD
Inspected, cleaned and restored over 2,500 LF of sanitary sovent riser piping.
Built in 1982, FL
CIPP lining 35 sanitary riser stacks and underground mains approx. 4,000 LF of piping without stopping operation or removing guests.
Built in 1985, FL
CIPP lining underground plumbing approx. 1,500 LF of piping, including excavation on the interior to repair collapsed piping.
Built in 1973, FL
CIPP lining sewer riser stacks, relining of approx. 3,300 LF of piping.
Built in 1954, FL
CIPP lining and pipe replacement of 32 sanitary riser stacks and clean underground approx. 3,200 LF of piping.
Built in 1976, FL
CIPP lining sanitary riser stacks and underground mains approx. 7,800 LF of piping to include utilities and extended bath branch laterals.
Built in 1975, FL
CIPP lining 120 sanitary riser stacks and underground mains approx. 7,250 LF of piping, including excavation on the exterior of the buildings to repair broken piping.
12 Buildings, Built in 1970, FL
CIPP lining underground mains and laterals approx. 3,000 LF of piping
Built in 1973, FL
CIPP lining 72 sanitary riser stacks approx. 3,000 LF of 2” and 3” cast iron piping.
Built in 1973, FL
CIPP lining 109 sanitary riser stacks, rainwater leaders and underground mains approx. 4,500 LF of piping.
Built in 1990, FL
Inspected, cleaned and restored over 13,000 LF of cast iron sanitary sovent riser stacks and pipe replacement, (after several unsuccessful attempts by previous contractors).
CIPP lining underground storm piping over 1,000 LF of 42”, 30” and 24”.
Built in 1968 & 1964, FL
CIPP lining 35 sanitary riser stacks and underground mains approx. 4,250 LF of piping, including repair to broken piping.
Built in 1953 & 1980, FL
CIPP lining underground plumbing approx. 1,500 LF of piping.
Built in 1972, FL
CIPP lining underground mains and laterals.
Inspect, clean and line CIPP storm collection system.
Cleaning of over 500 LF of bulk handling troths and close to 5,000 LF of 6” and 10” carrier pipes in a 100% dry containment.
Built in 1970, FL
Inspect, clean and CIPP lining over 4,000 LF of sanitary riser stacks and underground piping.
Built in 2006, MD
Inspected, cleaned and restored over 15,800 LF of sanitary sovent riser piping.
We relined a damaged 24-inch industrial drain that was taking in sand and rock.
We planned the restoration of 69 sewer stacks in an occupied 18-story tower.
We cleaned and camera-inspected the drains across a working museum campus.
We cleaned and lined more than 300 feet of main sewer with overnight work, excavated and replaced the cleanouts, and vapor-tested for the reported sewer gas.
We identified 19 stacks for rehabilitation and inspected, cleaned and repaired about 1,300 feet of pipe, combining lining with partial replacement.